- Front end Engineering Design
Challenge
Penspen was commissioned to carry out the Front End Engineering Design for the 24” diameter high pressure gas pipeline from Gainsborough in Lincolnshire to West Burton Power Station in Nottinghamshire in 2007/8. We were then commissioned to oversee pipeline construction and pre-commissioning in 2009, and commissioning in 2011.
Services
- FEED during 2007/8
- PMC during construction
- Assist in Commissioning in 2011.
Solution
Penspen achieved all client objectives, using a Pipeline Contractor (PPS) that recorded no Lost Time Injuries and an excellent safety record.
Result
EDF Energy received a safe and efficient fully functioning pipeline on time and on budget.
Más información sobre este producto consulte en: http://www.penspen.com/experience/west-burton-gas-pipeline/
Servicios y capacidades
Consulta disponibilidad, configuración, dimensiones, compatibilidad, capacidad, transporte, montaje y condiciones comerciales directamente dentro de IndustriaMinera.cl.
Empresa: Penspen Integrity
Formulario de Contacto
* Solicita información referida a West Burton Gas Pipeline a Penspen Integrity.